87% of the Anthropic power will come from gas and 11% from coal in 2028
TL;DR Highlight
Analysis of Anthropic's contracted data centers: 87% gas, 11% coal power in 2028
Who Should Read
A developer who picks LLM API vendors and wants to understand the power and carbon impact of AI infrastructure
Core Mechanics
- No direct US renewable commitments
- Anthropic's disclosed renewable deals are only in Norway and Canada as of November 2026.
- It did secure commitments for 1.7 GW of gas generators for $3.4bn.
- 87% gas, 11% coal in 2028
- As of October 2026, Anthropic has contracted 15 GW of compute, with 5.9–9.6 GW tied to specific sites.
- Without renewable commitments, new grid load is assumed to be met by marginal fossil generators.
- Mid-case 32 million tons CO2 in 2028
- The range is 17–38 million MtCO2e.
- The mid-case exceeds California's total power generation emissions (31.1 MMtCO2e in 2024).
- Google, Microsoft and Meta 2025 location-based Scope 2 were 15, 12 and 5.9 million.
- Carbon intensity 35% above US average
- Anthropic's power is estimated at 1,033–1,076 lb CO2e/MWh.
- The US grid average is 767 lb CO2e/MWh.
- 80% of on-site power is inefficient
- On-site behind-the-meter gas is about 25% (2.5 GW) of contracted power.
- 80% of that is simple cycle turbines and engines, which pollute more than combined cycle plants.
- $2–3B yearly health damages
- Estimated emissions exceed 13,000 tpy NOx and 2,000 tpy PM2.5.
- Colossus 2 gets most power from temporary unpermitted turbines, most without SCR.
Community Reactions
- Commenters criticized the lack of US renewable commitments
- They noted Alphabet has made many, and cited pollution in Memphis from leasing Colossus 1.
- Commenters questioned the analysis assumptions
- Marginal capacity is nearly all gas and coal, so grid sites are treated as over 99% fossil.
- The short-term focus ignores long-term grid adjustment.
- A commenter blamed regulation for on-site gas
- They said NEPA and environmental reviews leave renewables stuck waiting for grid connection.
- They argued grid connection would let wind and solar displace gas.
- A commenter compared regional carbon intensity
- They cited about 5 gCO2/kWh for French nuclear, 300–350 for gas and 800–900 for coal.
- They said a gas turbine takes under a year to set up versus about 10 years for nuclear.
How to Apply
- Build a vendor power checklist
- In 30 minutes, tabulate your LLM vendors' renewable deals, data center locations and emissions reporting.
- Leave unknowns blank and turn them into questions for the vendor.
- Log inference calls for ESG reporting
- Record model, region, call count and token count per request.
- Multiply by vendor emission data once it is published.
- Add power source to vendor selection
- If customers ask about carbon, add power mix and region columns to your vendor comparison.
- If you can pick a region, verify its grid mix in documents.
Try It
# Paste into Claude or ChatGPT (the source is a report, so this is a simple checking prompt)
Our service calls the LLM API of {{provider name}} in {{region}} about {{call count}} times per month.
We need to explain the environmental impact of our AI features to customers.
Write questions I should ask the provider on each item:
1) Data center power mix (gas, coal, nuclear, renewable)
2) Whether renewable contracts or investments are disclosed
3) Use of on-site generation and emissions controls
4) Emissions reporting method (Scope 2 / Scope 3)
Do not guess unverified facts; mark them "needs provider confirmation".
Next: paste the answers into your vendor comparison table and look for blanks.Terminology
Related Papers
A Beginner's Guide to Local AI with Inkling, Qwen, and Unsloth
Install Unsloth Desktop, load a quantized Qwen model, and share a private ChatGPT-like AI on your home LAN.
Muru – AI-assisted Rust server for Python apps by mod_WSGI's creator
mod_wsgi's creator is building Muru, an AI-assisted Rust ASGI/WSGI server, documenting it in public
Anthropic’s Nasdaq debut
Anthropic listed on Nasdaq and closed its first day below its opening price.
OpenAI still has a WebRTC Problem
WebRTC drops late audio, hurting voice AI; MoQ retransmits and buffers instead
Gemini 4 Neon
Gemini 4 Neon cuts cost per task 32% versus Carbon, at $3 input and $15 output per million tokens
AI is killing All About Berlin
After Google AI Overviews, a Berlin guide site lost 70-75% of its traffic.
Not Everything Needs an LLM
PostHog used small decision models to skip 98.7% of expensive LLM calls
GPT‑6.2 Astra and Sol
GPT-6.2 Astra and Sol cut costs sharply, but over-engineering and early-stop reports are mixed